Foreign Line Crossing Survey
To identify pipeline operators who have intersecting facilities, SKW conducted field site inspections and determined GPS coordinates for their locations. Stray current surveys were then performed at each location. The data collected was evaluated and corrective measures were taken as needed (excavation; installation of anodes or bonds; and installation of test leads for monitoring purposes). Test leads were then installed at the remaining locations. SKW also reviewed alignment sheet stationing and made corrections as needed.